Monitoring The monitoring section describes the monitoring equipment and provides recent results from the various monitoring stations.

Following the cessation of plant operations in August 2003 PKC reviewed the environmental monitoring for the site in consultation with the EPA, DIPNR and WCC to develop a program appropriate to the reduced activity during the care and maintenance period.  PKC will continue to undertake dust deposition monitoring at three locations during the care and maintenance period, along with HVAS monitoring at the Old Port Kembla Fire Station.  Monitoring requirements will be reviewed periodically with the appropriate regulators.

 


If you would like any further information or have any matter which should be brought to our attention, please call our 24 hour Community Line on 1800 688 587. This is a free call.


Copyright © Port Kembla Copper Pty Ltd 2000
E-mail: pkcinfo@pkc.com.au
Last updated  November 17, 2004
Created by Bailey Bailey & Bailey - updated by PKC staff